Back up config file
Store it somewhere safe (PC, cloud, or a USB stick) -
-Document My system-
Make note of current dataset layout, apps, network settings, ACLs, and any auxiliary parameters. -
-Check release notes-
Look at iXsystems Release Notes for Electric Eel to see new features, known issues, or deprecated options -
-Remove custom auxiliary parameters-
as they may break between major versions. If I rely on any, list them out so I can re-add later if needed. -
-Ensure backups for critical data-
Snapshots on pool are good, but ideally have at least one external backup for peace of mind. -
-Verify Apps & Services-
If using TrueCharts, confirm the train is compatible with Electric Eel. (noted I saw alot of reviews/people talking about how Nextcloud did not play well with the new update to Electric Eel -
-VMs & Containers-
Make sure VMs shut down cleanly.
Export any critical VM configs if possible.
8.-Post-Upgrade Steps-
Confirm Boot Environment…
After reboot, check that Electric Eel is now the “Now/Reboot” entry under System Settings.
- -Ensure SMB, NFS, and network settings are intact.
Check Apps → confirm they started. If not, redeploy from config.
10.-Update All Apps If Needed-
Once on Electric Eel, update apps to their latest versions.
11.-Run Health Checks-
Storage → scrub pools.
-Ensure SMART tests are still scheduled-
-Verify UPS service-
12.-Rollback Plan (If Things Break)-
If Electric Eel gives Me problems:
Reboot Into last Dragonfish boot environment.